Sewer system Veliki Gaber

PROJECT DESCRIPTION

The municipality of Trebnje was successful in applying the project »Sewer system Veliki Gaber« to the Second public tender for the priority axis of "regional development programs" under the Operational Programme for Strengthening Regional Development Potentials for the period 2007-2013, development priority »Development of Regions". The sewer system collects urban waste water from the settlements in the northwest area of the Municipality of Trebnje, so that all the effluent water flows to the waste water treatment plant of a capacity of 1,000 PE in the settlement of Medvedjek. Works performed: construction of gravity sewer lines in the length of 7,232 m; construction of sewer pressure lines in the length of 1,302 m; construction of three pumping stations and construction and installation of sewage treatment plant (WTP 1000 PE).

OBJECTIVES AND PURPOSE OF THE PROJECT

The municipality of Trebnje has opted for a professional and comprehensive approach to address the problem of collection, disposal and treatment of wastewater in the northwest area of the municipality.

FINANCING

  • Ministry of Economy and Technology 588.954,08 €
  • Municipality of Trebnje 551.445,65 €
  • Total project value = 1.140.399,73 €
     

IMPLEMENTATION

September 2008 – June 2010
 